BLOG

Modular Solar Panel Systems Design: 5 Considerations

When designing a modular solar panel system, it is necessary to consider module power (such as 300W~400W standard modules), series-parallel configuration, inverter compatibility (such as MPPT range 150V~450V), installation angle optimization of power generation efficiency and expansion reserve to ensure the system is flexible and reliable. 



Module Matching


Last summer, a photovoltaic factory just put into operation encountered a strange problem - the EL detector screen suddenly showed black spots, like ink drops on an X-ray film. The engineers investigated for three days and nights and finally found that the voltage window difference between N-type cells and P-type inverters was 0.8V, which was equivalent to installing double shoes of different sizes in the system.

This is not an isolated case. The SEMI PV22-036 report shows that 23% of power station efficiency losses are caused by module matching issues. I have been engaged in monocrystalline process for fifteen years and have handled 12GW projects, witnessing too many "forced marriages" tragedies. Take the most critical voltage matching as an example. Nowadays, the open-circuit voltage of market modules ranges from 42V to 52V in a complete mess, but many installation teams are still using the parameter tables of inverters from five years ago.

Module Type

Operating Voltage Range

Temperature Coefficient

Lessons Learned

N-type TOPCon

38-42V

-0.28%/℃

A project had 23% difference in power generation between winter and summer

P-type PERC

32-36V

-0.35%/℃

A plateau power station triggered overvoltage protection

HJT bifacial

40-45V

-0.25%/℃

Snow reflection caused MPPT to jump erratically

Last year, when diagnosing a power station in Qinghai, we encountered a typical case. They mixed two types of silicon wafers - 158.75mm square mono wafers with 182mm quasi-square mono wafers. On the surface, the sizes were similar, but the minority carrier lifetime difference was actually 3μs. This is like using a Moutai bottle to hold Erguotou. The IV curve test showed no problems, but the actual CTM loss rate during power generation was 5.8% higher.

Now there is a deadly misconception in the industry that high-efficiency modules can be installed blindly. A batch of 182 mono cells (SEMI PV23-115) showed in field tests in Guangdong's humid environment that modules with 23.6% efficiency actually output 11.7% less than the nominal value due to insufficient cable current-carrying capacity. This is like putting 92-octane gasoline in an F1 car - no matter how powerful the engine is, it will stall.

· For every 1mm² reduction in cable cross-sectional area, system resistance increases by 0.4mΩ

· When ambient temperature exceeds 25℃, P-type module CTM loss rate jumps by 1.2-1.8%

· Poor heat dissipation in junction boxes causes 0.05V/day voltage drift

When helping a fishery-photovoltaic complementary project in Jiangsu with renovation, we found they had standardized the bracket angle to 37 degrees. But the site had both bifacial modules and single-sided glass, with backsheet power generation differing by 15%. This is like making ballet dancers and boxers wear the same size shoes for training, and the final disconnection rate of the two inverters soared to 4.7%, watching the money go down the drain.

Nowadays, savvy design institutes are playing new tricks - using dynamic matching algorithms instead of static parameter tables. Just like a 200MW project in Zhejiang last year, where a micro weather station was installed for each string to adjust the MPPT operating point in real time. According to IEC 62108-2023 certification data, this system actually increased power generation by 8.3% during cloudy weather.

The most troublesome issue is still the grounding system matching. Last month, when disassembling a burned junction box at a power station, we found a potential difference of 0.15V between the galvanized steel bracket and the aluminum alloy frame. This thing is not obvious on a regular day, but in humid weather, it becomes a "chronic electrical cancer." After two years, the string attenuation rate is 2.3 times the normal value.




Bracket Load-bearing


Last summer, a N-type module factory had an incident - after the typhoon season, the customer sent photos: the entire array's western side brackets were twisted into a pretzel, and the 25mm C-shaped steel broke into three pieces. After checking the data, the design institute calculated the load based on a conventional 25m/s wind speed, but the actual instantaneous gust reached 34m/s, which directly sounded the alarm for photovoltaic bracket design.

Bracket load-bearing is not like playing with building blocks. You first need to understand what the roof is "bearing." Take the common color steel tile roof as an example, if the purlin spacing exceeds 1.5 meters, you need to add cross beams, otherwise the thin steel plate will show you "collapse waist" at any time. When I went to a car factory's roof for a site visit, the construction team didn't pay attention to the purlin direction and installed the brackets right at the joint of two steel plates. Before the rainy season was over, the fixing point had torn a 3-centimeter opening.

Material Type

Ultimate Load Capacity (kg/m²)

Cost Coefficient

Applicable Scenarios

Q235 Carbon Steel

65-78

1.0

Conventional industrial and commercial roofs

Aluminum Alloy 6061

48-53

2.3

Lightweight carports

Stainless Steel 316

82-90

4.1

Highly corrosive offshore projects

At the beginning of this year, when helping a chemical park with a solution, we encountered a typical problem: the originally designed live load of the factory roof was only 0.3kN/m², while the photovoltaic system's self-weight plus wind and snow load calculated to 0.55kN/m². The final solution was to change the bracket foundation from single-point fixation to distributed load-bearing beams, which is equivalent to changing the elephant's footprints from pillars to snowshoes, tripling the contact area.

When it comes to dynamic loads, many beginners will stumble in snow load calculation. A 5MW project in the north suffered from this - the design used a 50-year return period snow pressure value, but the actual snow thickness exceeded the calculated value by 40%. Now industry veterans know that brackets with a slope angle less than 10° must be equipped with anti-slip baffles. This seemingly insignificant thing can withstand the shear force generated by snow sliding in critical moments.

· The selection of color steel tile clamps depends on the wave height: use flat-head clamps for wave heights below 28mm, and switch to eagle-beak type for higher ones

· Concrete counterweights should not be placed directly on the waterproof layer; an EPDM rubber pad must be placed in between

· For coastal projects, bolts must be inspected monthly, as salt spray corrosion can shrink M12 bolts by 0.5mm in half a year

A typical lesson from a photovoltaic carport project was that the design didn't consider the vibration load from vehicle entry and exit, and the bracket connection parts became loose by 17% within half a year. Later, we added Loctite243 threadlocker to the bolts, and vibration tests showed the loosening probability dropped by 86%. Bracket load-bearing is essentially a guerrilla war against Newton's laws - you never know which direction of force will suddenly stab you in the back.

When it comes to detection methods, cutting-edge construction sites are now using laser displacement meters to monitor bracket deformation in real time. The data from a GW-level project is very interesting: when the module temperature rises to 65℃ at noon, the bracket's lateral displacement is 2.8mm more than in the morning. This reminds us that when doing structural calculations, we must consider the material's thermal expansion coefficient, especially for power stations that operate across seasons.




Wiring Planning


When diagnosing a coastal photovoltaic project last year, the EL detector alarmed as soon as it started - three groups of module strings showed earthworm-like black spots, and the operation and maintenance team was sweating with anxiety. After checking, it turned out that the construction team cut corners by replacing 4mm² cables with 2.5mm², and the line loss rate directly soared to 8.7% (SEMI PV22-019 stipulates that industrial and commercial projects must not exceed 5%). As a photovoltaic system designer who has handled 23 distributed power stations, I have stepped on all the pits in wiring planning.

Battlefield Lessons:
A food factory roof project (grid-connected in 2023) had a CTM loss rate 1.8% higher than the design value due to crossing wiring. The EL imaging showed seven modules had diagonal hot spots (IEC 61215-2023 standard test number #CT20245). When the junction box was disassembled, it was found that the DC cables were abraded at three places, exposing the insulation layer.

Now, when planning wiring, I always have three windows open on my computer: PVsyst simulator, cable current-carrying capacity table, and site aerial photos. Missing any one of these makes it hard to sleep at night. Especially when dealing with factory roofs with ventilation ducts, the wiring path is more exciting than playing Snake.

Cable Size Selection

Normal Current

Safety Threshold

Pit Warning

4mm² Copper Cable

≤41A

Temperature >60℃ reduces capacity by 15%

A project triggered overload protection due to poor heat dissipation from color steel tiles

6mm² Copper Cable

≤53A

Bending radius must be >8 times the cable diameter

Tight turns caused insulation layer cracking

A more absurd case I dealt with last week was a logistics park project where the string voltage difference was as high as 22V. After scanning with a thermal imager, three MC4 connector locations were 19℃ higher than the ambient temperature (on-site data recorder number #THX2024-0712). When the waterproof tape was peeled off, it was found that the construction team had mixed connectors from different manufacturers, causing the contact resistance to double.

· Go straight? You need to check if the brackets have equipotential bonding

· Go underground? Water can breed fish in aluminum alloy rails

· Go through cable trays? Electrochemical corrosion between stainless steel and galvanized parts is a big problem

The strict rule I set for my team now is: an IV curve detection point must be installed every 20 meters (refer to IEC 62446-2016 standard). In a villa project last time, just because the wiring from the inverter to the module was 15 meters longer, the MPPT tracking efficiency dropped directly from 99.2% to 94.7%. When the owner came to question with the electricity bill, the feeling was worse than being caught cheating on an exam.

Recently, I've been studying the requirements of the new national standard GB/T 34932-2024. The cable fixing spacing has been reduced from 1 meter to 0.8 meters. A project I did in Shandong last month found that when the wind speed exceeded 8m/s, the swing amplitude of suspended cables exceeded the safety value by 2.3 times. Now I always carry anti-wind zip ties in my toolbox and want to reinforce any loose cables I see.


Inverter Selection


When diagnosing a 50MW power station in Gansu last year, we found that their centralized inverter caused the power generation of the entire string to drop by 23% when the EL black spots spread - this was like having the wrong blood vessels connected to the heart. Although individual module efficiency was still acceptable, the entire string was dragged down. Anyone who has designed photovoltaic systems knows that inverter selection directly determines whether your power station is "lively and jumping" or "paralyzed".

First, a counterintuitive point: bigger inverters are not always better. Last year, a 3.6MW distributed project in East China had the owner insist on replacing a 150kW inverter with a 175kW one. As a result, the MPPT (maximum power point tracking) efficiency dropped from 98.7% to 94.2% in high-temperature environments in summer. This is like a small horse pulling a big cart will die of exhaustion, and a big horse pulling a small cart still can't run fast - same principle.

· Input voltage range is more important than nominal power: especially during weak light periods in the morning and evening. For an 182 module array in foggy weather, the output voltage may be as low as 520V. If the inverter's startup voltage is set above 550V, it's equivalent to wasting 1.5 hours of power generation time every day

· Don't be fooled by the number of MPPT channels: A brand advertised 6 MPPT channels looked great, but actual tests showed that when more than 3 channels worked simultaneously, the tracking accuracy degraded from ±0.8% to ±2.3%

· Cooling design hides devilish details: An inverter used in a northwest project was labeled to operate at full load under 40℃ ambient temperature, but on-site measurements showed the internal IGBT module temperature soared to 87℃, triggering derating

Parameter Type

Desert Power Station

Coastal Distributed

Mountainous Project

Protection Rating

IP65 dustproof > IP54

IP66 corrosion-resistant > conventional

IP67 waterproof essential

Nocturnal Self-consumption

<5W

<8W

<20W

MPPT Current

13A is sufficient

Needs to support 16A+

12A is suitable

When debugging a fishery-photovoltaic complementary project in Guangdong last year, we found that the inverter manufacturer's "±5% overloading capability" couldn't withstand real-world testing - when the module's actual power exceeded the nominal value by 3.8%, the DC input side frequently triggered overload protection. Later, we used the dynamic load test method from IEC 62109-2 standard to re-verify and discovered that this manufacturer's topology circuit design had inherent flaws.

Now there's a new pit in the industry: bifacial modules paired with traditional inverters will suffer. We tested a bifacial project where when the backside gain reached 21%, the conventional inverter's DC input overvoltage protection point would act prematurely. At this time, you need to choose a special model that supports 1000V+ DC voltage or switch to a smart dynamically adjusting model. For example, Huawei's "string doctor" function last year indeed dug out an additional 3% power generation.

Recently, when helping a wind-sand area project in Inner Mongolia with inverter selection, I found that the international brand's fan lifespan data was misleading - the advertised 100,000 hours was tested at 25℃ in the lab, while the actual operating environment on-site was 45℃ + sandstorm. Later, we switched to a domestic magnetic levitation fan solution. Although it was 800 yuan more expensive per unit, the maintenance cycle was extended from half a year to two and a half years.

A point that must be emphasized here: don't blindly believe the manufacturer's conversion efficiency curve. Last year, a top 5 manufacturer's promotional brochure claimed "European efficiency of 98.6%," but when recalculated using China's typical climate weighting algorithm (CQC3306-2018), the actual value was only 97.2%. Now we require manufacturers to provide measured data for 10%-100% load points, especially the efficiency at 30% load rate, which is more important for distributed projects than peak efficiency.

Expansion Reserve

The scene of a photovoltaic power station's expansion failure last summer is still painful to me - at 40℃ high temperature, engineers had to cut into the aluminum alloy brackets with a cutting machine to add new modules, and the CTM loss rate directly soared to 3.8%. This is like adding floors to a house but forgetting to leave a stairwell, forcing people to dismantle walls on-site.

The physical margin of bracket structure is the easiest pit to fall into. Among the projects I've handled, 80% of expansion disputes are concentrated on the load-bearing margin of transverse rails. For example, an 182 module array initially designed with C-shaped steel rails, but when upgraded to 210 large-sized modules the next year, the rail deflection exceeded the standard by 2.3mm/m. The reliable practice now is:

· Reserve 5% adjustment space for longitudinal column spacing (don't fix it at the ground bolt position)

· Pre-install at least 30% redundant clips for rail connectors

· Design the cable channel diameter at 150% of current needs

Expansion Plan

Initial Cost Increase

Later Retrofitting Cost

Full Configuration Design

+18%

0

Conservative Reserve

+8%

50,000-120,000 yuan/MW

No Reserve

0

200,000 yuan/MW and above

When upgrading a distributed project last year, we found that the cable current-carrying capacity at the grid connection point was insufficient and critical. The original 250A circuit breaker had to carry an additional 320A current, forcing us to replace the copper busbar that night - this core module is like the cardiovascular system of a person, with surgical risks ten times higher than installing a stent.

Now, when encountering DC-side overloading designs, I strictly require fuse specifications to be selected at 1.5 times the actual current. One pit many people overlook is the impact of temperature on current-carrying capacity: for every 1℃ increase in ambient temperature, the rated current must be reduced by 0.5%. A coastal power station (SEMI PV22-109) last year suffered from melted DC cable insulation due to 40℃ high temperatures in summer, resulting in 23 days of lost power generation.

Recently, when helping a state-owned enterprise retrofit a 2018-built old power station, their original centralized inverter was a complete "expansion black hole." Now they want to add 30% capacity, but found that there weren't enough MPPT channels, and the AC cabinet terminal blocks were also full. This case tells us: the inverter capacity can be small, but the interfaces must have a 20% surplus - just like home renovation should leave more socket holes.

A counterintuitive point to make here: don't pack the module layout too tightly! For ground power stations, leave at least 1.5 times the module width of space between each row. A northwest power station (IEC 62108-2023 certified project) suffered from this - when expanding, they found the cleaning vehicle's turning radius was insufficient and had to dismantle 12 already installed arrays and re-layout.

In a fishery-photovoltaic complementary project I'm currently working on, the bracket foundation was specially designed with adjustable-height piles. Although this design was 15% more expensive initially, the adjustment efficiency when adding tracking systems later improved by 60%. Remember: good expansion design is like Lego blocks, and each connection point must consider possible deformations in the next 3-5 years.